Earlier inspections showed that some minor clearance has arisen in the vertical direction between the foundation pier and the transition piece. In collaboration with Bouwcombinatie Egmond we worked out a repairs plan, which will now be rolled out.

The foundation piers of three turbines will be filled up with concrete. This will form a solid basis and will prevent a further shifting. For this purpose, the ship will be equipped with concrete silos and pumps, among other equipment. We expect that the work at sea will start in a few weeks time.