When it arrived at the location the Svanen dropped anchor. With the aid of the ship’s crane the foundation pile was place vertically on the sea bed; the pile driver was then lowered onto the pile so as to drive it approximately 30 metres into the sea bed. A transition piece, which clears the water by around 13 metres, is mounted onto the pile. Attached to this transition piece are work platforms, ladders and a berthing facility for boats. The installation of the towers and turbines will start in June. For more information about the construction